| - A Maintenance planning and scheduling
article focusing on management of shutdowns by DAVE KRINGS,
Dave Krings is maintenance planning coordinator
for Potlatch Corp., Minnesota Pulp and Paper Div., Cloquet, Minn.
Potlatch Cloquet's low-cost maintenance shutdown management techniques
focusing on type, quality, and timing of work contribute to an 83% drop
in maintenance cost per ton.
Effective shutdown management is critical to the operation of mills,
for without well-planned and executed shutdowns, equipment reliability
suffers, and the mill pays the price in poor quality and lost production.
Becoming proficient at managing shutdowns is a way to reduce overall downtime
costs so that shutdowns themselves do not consume the savings they are
capable of generating.
Due to current economic conditions, cost cutting has become a high priority,
and effective shutdown management is an exercise in such waste reduction.
Maintenance shutdowns are a major part of the annual budget at most mills
and are usually a target for cost reduction. However, maintenance shutdown
costs can be reduced by 30% to 50% from historical levels if startup after
the outage occurs smoothly and predict-ably. By using simple and effective
shutdown management techniques, savings equal to several weeks of additional
production each year can be achieved. These improvements can occur without
sacrificing any work or canceling any scheduled maintenance downtime.
If the principles of successful shutdown management are clearly understood,
the actions needed to make shutdowns more cost-effective can be taken
immediately. When a mill decides to identify major outage work far in
advance and the work is carefully planned to maximize ease of execution,
the result will be lower costs. If, at the same time, disruptions to the
process (such as late add-on work) are kept under control, there will
be sufficient resources available to continually refine and improve the
shutdown model for greater savings each year.
Shutdowns have a serious impact on mill profitability, and low-cost shutdown
management techniques are different from traditional practices. Three
important concepts that differentiate a well-managed, low-cost shutdown
from a poorly managed one are:
- The type of work that is executed during the shutdown;
- A finalized schedule for the shutdown work list;
- The quality of the shutdown work planning.
TYPE OF SHUTDOWN WORK IS CRUCIAL. It is vitally
important that the shutdown work list be kept as short as possible. Keeping
the list short is both the means to reduce costs and the primary method
for focusing on work that can only be performed during a major outage.
All other work is deferred to a time outside of the shutdown window.
The main activity during the shutdown should be preventive in nature (including
equipment inspections), followed by cleaning and repairs. When this basic
concept is followed, it results in reduced overtime, lower contractor
costs, and superior documentation. It also almost guarantees that the
budget will be met. For example, using the short work list method during
the 2001 utility outage at Potlatch's Cloquet, Minn., mill, the power
and recovery department completed its work within 3% of the budgeted cost
for the second year in a row.
Initially, many mill personnel at Cloquet believed it was best to execute
as much work as possible during a major outage. However, after shifting
to the short work list approach, there have been marked improvements in
budget control, overall outage cost, equipment reliability, and planning
efficiency. There has also been a reduction in the use of contract labor
for outage re-pairs due to increased availability of maintenance personnel
during major outages. The culture within the mill is slowly changing to
one where the total cost of each activity is considered before action
is taken.
Previously, the Cloquet mill had been pressured to eliminate scheduled
minor repair days by executing such work during a major outage. The intended
result was to reduce downtime, thereby increasing production. However,
in practice, the additional costs for overtime labor, expedited parts
delivery, execution of unplanned work, and reduced worker efficiency during
extended overtime exceeded the apparent savings.
Major shutdowns should not be used to avoid periodic minor downtime. Minor
downtime is an important part of proactive maintenance because it provides
an opportunity to perform periodic preventive maintenance and repairs
that cannot be done during operation. Each mill must determine the frequency
of its planned minor downtime events, and once an effective cycle is established,
it should not be needlessly interrupted. In all areas where a yearly downtime
schedule is established and followed, the Cloquet facility has experienced
record production, improved quality, and increased reliability.
There is a delicate balance between scheduled downtime and plant reliability.
Major shutdown work is intended to support maintenance efforts carried
out until the next major shutdown, including minor downtime repairs. An
effective measurement technique is available to help in determining whether
outages and other maintenance work are providing maximum value. If the
ratio of the mean time between production loss (MTBPL) and mean production
loss (MPL)1 are tracked over time, one can readily see if the plant is
experiencing greater reliability and less severe failures (Figure 1).

FIGURE 1. Increasing mean time between production
loss (MTBPL) versus mean production loss (MPL) indicates that the efforts
of maintenance and operations are improving productivity.
Production loss is defined as any loss of capacity, whether scheduled
or unscheduled.
By adjusting the time between scheduled shutdowns and the duration of
the shutdowns, maintenance and operations continuously work toward increased
uptime. Monitoring MTBPL/MPL while making adjustments to the shutdown
events gives an almost immediate indication of success or failure. Many
times, productivity will increase when more frequent or longer shutdowns
are executed. This is due to the increased reliability that occurs when
equipment is properly maintained. This simple measure single-handedly
eliminates the conflict between production and maintenance personnel associated
with downtime repairs. When this balance is reached, everyone will see
it reflected in the data.
FINALIZED SCHEDULE FOR THE SHUTDOWN WORK LIST.
While a finalized schedule is not a budget development exercise, shutdowns
do have a significant impact on mill expenditures. Because of these budgetary
implications, a finalized schedule for the shutdown work list should incorporate
elements from both a long-term and a short-term plan for shutdown management.
A long-term plan for shutdown management should be outlined in the budget
forecast three to ten years before execution. The long-term plan contains
fairly detailed lists of the major work that must be performed during
each scheduled major shutdown. For instance, boiler inspections, relining
of large tile tanks, sewer repairs, and electrical power distribution
system inspections are estimated in the long-term plan. Funds must also
be included for smaller repairs required during the shutdown, which are
often estimated as a lump sum figure.
The long-term plan is the tool for controlling the scope of each outage.
Long-term planning is a critical and often overlooked piece of the proactive
approach to maintenance. Without a long-term plan, major repairs and inspections
often do not get adequate attention until it is too late to properly prepare
for their execution.
In addition, an operating budget should be constructed annually. In order
to accurately budget for a major shutdown, the scope, duration, and timing
of the outage should be supplied before the operating budget is approved.
This means that any major shutdown is scoped to an accuracy of +/- 10%
at least 18 months before it is scheduled to take place in order for the
budget process to proceed. This is the short-term plan for shutdown management.
The short-term plan is developed using the long-term plan as a starting
point. In addition to the major repairs, the short-term plan must include
detailed lists and estimates for the smaller, less costly repair work.
As the budget and shutdown plan enter the approval process, it should
be very clear what the upcoming outage will accomplish. It is relatively
easy to establish which projects are driving the outage. If this is not
the case, then a shutdown is not justified.
It is acceptable to allow limited rearrangement and substitution jobs
for a scheduled outage up to six months before it occurs, provided the
budget contains funding for the work. However, mill management should
seriously enforce the six-month lockdown, and any work proposed for addition
after the lockdown date should be carefully scrutinized. Usually, it is
necessary to cancel another job to make time and funds available to do
the additional work. If this rule is not enforced, planning efficiency
for the shutdown will rapidly drop to unacceptable levels.
Parts delivery issues also become a problem when jobs are added after
the lockdown date. Jobs added on short notice before a shutdown are generally
the cause of most disruption to planned and scheduled work. It is important
to remember that planning work is expensive, and cancellation of a job
that is already planned, with parts onsite, in order to do unplanned work
is extremely wasteful. Table 1 shows a comparison of departments during
a major outage at the Cloquet mill in 2001. The department using the proactive
method completed more work orders, although they requested 30% fewer jobs.
| TABLE 1.
Comparison shows results of 2001 major outage from two different departments
at the Cloquet mill. The department using the proactive method completed
more work orders, although they requested 30% fewer jobs. |
| Proactive vs. Reactive |
Proactive Shutdown Method |
Reactive Shutdown Method |
| Jobs scheduled before lockdown |
196 |
183 |
| Jobs added after lockdown |
0 |
56 |
| Jobs added during shutdown |
4 |
45 |
| Planned jobs completed |
193 |
131 |
| Unplanned jobs completed |
4 |
45 |
| Total jobs demanded |
200 |
284 |
| Total jobs completed |
197 |
176 |
| Success Rate (%) |
99% |
62% |
The use of specific, challenging lockdown dates is a concept that may
be difficult to accept for some individuals. The 18-month budgetary work
list is often misunderstood, because it is not always clear how one could
know in advance what repairs would be needed.
This is where planning comes into play. Each facility usually knows what
work is done during every outage. It is important to review repair histories
and make an educated estimate of the time, materials, and expenses that
commonly occur with each project. If this information is not readily available,
now is an appropriate time to start building a history file for all equipment.
Planning ahead for outages will get simpler as the proactive approach
gains acceptance. The key to making a reasonable estimate of future shutdown
work is to keep records of past shutdowns and refer to them frequently.
If maintenance planners are being used correctly, there will be complete
work instructions for each job that are reused and refined each year.
A word of caution is in order at this point. Do not estimate the budget
for shutdowns using budget figures from the past, without making any adjustments
for higher productivity. The budget figure will be significantly higher
than necessary if the plant has adopted the new methods. It is not uncommon
to achieve shutdown cost reductions of 50% or more. The best way to avoid
this problem is to adjust the historical budget using estimated labor
and material costs from the planner's work packages.
QUALITY OF THE SHUTDOWN WORK PLANNING. The quality
of the planning time that is invested in each shutdown will directly affect
the completed work. More work will get executed with fewer people, in
far less time, if it is well planned. Also, repair quality will increase,
and the cost for each repair will drop significantly. Unplanned repair
work orders taking eight hours to complete can take less than two hours
to execute when planned (on average). This is due to a combination of
better instructions; easy access to parts, tools, and materials; and better
coordination of resources. In some cases, the savings will be as high
as 90%. This has been verified in the field by maintenance technicians
at the Cloquet mill.
Each work order (sometimes called a job order or service order) should
be planned before execution. This includes all preventive maintenance
work, repairs, routine checks, contractor work, and capital projects.
It is very important that adequate personnel be dedicated to planning
work packages full-time. If this is not done, planners will often get
placed in the role of supervisor, craftsperson, or parts chaser. None
of these activities will increase the efficiency of maintenance activities
with the magnitude that planning will accomplish. Each planned job is
accompanied by a work package, which is a written document containing
all information needed to execute the work.
Any work that is placed on the shutdown schedule (or on any work schedule)
should be fully planned. If this is not done, it effectively places the
burden of planning the job on the craftsperson. This slows the work tremendously
and creates numerous opportunities for delays, mistakes, and confusion.
It is also much safer to execute planned work because the hazards are
methodically identified and avoided.
Technicians who are accustomed to working on planned jobs become the greatest
source of valuable information in the process. They identify weaknesses
in the planned work packages, and document these weaknesses for correction
if given adequate time to do so. As time passes, most routine repairs
will have work packages collected in the history file. When that happens,
the time required to plan repeated jobs in the future is reduced, and
the planners can shift their focus to continuous improvement efforts.
This is the point where proactive maintenance begins to save increasingly
large amounts of money. The knowledge base for doing maintenance activities
is then accessible to the entire workforce instead of only a few experts.

FIGURE 2. Maintenance cost per ton dropped 83%
over a four year period at the Cloquet mill. Plant improvements, combined
with a transition to planned maintenance activities, contributed to the
savings.
Figure 2 displays maintenance cost per ton of product (bleached market
pulp and coated free-sheet) at the Cloquet mill. In less than four years,
maintenance costs have dropped by 83% on a per ton basis. The savings
are partly attributed to improved maintenance practices and partly to
production equipment upgrades.