Lean Maintenance III |
|
|||||||||||||||||||
|
Feedback on this reliability article is appreciated. Send to info@idcon.com For plant maintenance consulting information. Please call (919) 847 8764. More information available in our reliability and maintenance books |
Read part 1 and part 2 and part 4 In the latest article I mentioned several areas that have to be improved for an organization to become lean. The focus in”lean thinking” is to reduce or eliminate losses. In this column I like to discuss what I call “Lean Shut Down Management”. Depending on the industry a shut down can be different in scale, for example:
NASCAR is a good example of what can be accomplished through precision planning and scheduling and execution. Major contributors to their pit stop, or shut down performance, include operations and maintenance communication and continuously working on improving the basics of Planning and Scheduling, Execution and Root Cause Problem Elimination. In the nineteen fifty’s a good pit stop lasted around 240 seconds. If nothing had been done because everyone thought this is very good, then we would still have four minutes pit stops, but the crew that could bring it down to where it is today, at a record 12,6 seconds, would win the race.
The driver of the car is in constant contact with the pit stop crew, they do not show up suddenly telling the pit crew “I think I have a problem with the right front tire” and the crew answers “We will go to the store and check if we have any replacement tire”. But this happens daily in most plants. In a NASCAR race there is a strong motivation to win the race, in a plant there might be completely other factors driving motivation. In addition to driving Planning and Scheduling to precision and excellence NASCAR pit crews are continuously working on improving the basics. This includes;
Regardless of the length of the shut down, the same principles apply to make the shut down more effective or what we like to call lean.
The combination of how many shut downs you have and how long they are affects your production volume and your ability to deliver products on time. It is a given that the shut down must be scheduled (when and who executes what) and that all the jobs must be planned (what, how, all the tools, spare parts and materials, lock out tag out etc. identified) before the shut down begins. All shut downs should also have a time for freezing the schedule. After the freezing point in time no new jobs will be accepted without harsh criticism. Two measurements can be used to challenge your organization and to measure and show improvements.
Define a scheduled shut down as a scheduled shut down if it is done within the agreed upon time-frame. For example, 44 hours before a shut down for an eight hour shut down on a larger process line, four weeks before for a three week long shut down in an oil refinery and four hours for tool changes that has been scheduled to take approximately forty minutes. Then measure how many jobs that are added or changed after the freezing point in time and during the shut down. Scrutinize all the added or changed jobs at latest, three days after the shut down. Have them explained and learn how they can be avoided next time you have a shut down.
With the same definition as in the previous paragraph, we can measure the relationship between scheduled and unscheduled shut downs. For many process industries the quota of the equation is over 1 and should steadily increase. This is on the condition that scheduled shut downs are not programmed and based on old habits but based on market and condition monitoring of process and equipment. Do all jobs need to be done during a shut down? You should also always ask if the jobs that are done during the shut down could be done during production. One good example of innovation and new thinking is to change the joints electric power high voltage lines. With the help of a helicopter and dynamite the old joints are improved without disruptions in power supply.
|
|||||||||||||||||||