Optimizing your Shutdown Program in 5 steps

by Greg Gustafson

Manufacturing facilities know downtime is money.  Every hour you are offline for a shutdown (SD) is costly from both lost revenue and cost of the workforce employed to maintain the facility.

 This article will discuss the 5 steps to Best Practices that will optimize your shutdown program. 

Step 1: Strategic Review

Step 2: Work Scope Review

Step 3: Execution Planning Review

Step 4: Integrated Schedule Review

Step 5: Close Out Review

 

 Step 1: Strategic Review

By optimizing your SD timing and drivers, you’ll generate a significant opportunity to improve mechanical availability, particularly if your facility has alternate production capacity and intermediate storage.  The best practice is to complete a strategic review; by doing so you’ll be able to optimize the timing of any shutdown taking interactions with other plant and facility operating areas into account.

Step 2: Work Scope Review

Reducing the cost of SD is easy when you eliminate work scope, however it’s not as easy to account for the consequences of the change.

In a best practice program, plant personnel are assisted through a risk-based decision making process…achieving cost savings by eliminating work, deferring work, or changing techniques to deliver the same or better results with lower risk exposure.

Step 3: Execution Planning Review

The third step in your SD process should be the execution planning review; this is designed to prepare the best contracting and work plan to reduce the mechanical path duration.  Best Practice is to you must go through all possible options ensuring it meets the SD requirements.  Once the contracts are in place, you then need to review the overall critical path for the turnaround.   You should review in detail work patterns, parallel activities, rescheduling techniques, and labor-loading profiles; make any revisions and finalize.

Step 4: Integrated Schedule Review

This step looks at the process critical path in order to reduce overall raw material in to product out time and minimize the risk of schedule deviations.  Best practice is to apply proven techniques to shutdown, de-commissioning, re-commissioning, start up schedules and procedures.  You must have a best practice team in place whose job it is to focus on integrating the process and mechanical schedules to further minimize unit downtime.

Step 5: Close Out Review

This is an integral step in the process…you must ensure that lessons learned during the shutdown are documented and used to enhance future shutdown plans.  If you bypass this step you are bound to make the same or similar missteps at the next shutdown.

 

By following these steps you will be adding efficiency and minimizing downtime.