Reliability and Maintenance Management
Consultant Idhammar is president of IDCON,
Raleigh, NC, a reliability and maintenance
management consulting firm, specializing in education, training and
implementation of improved operations, reliability,
and maintenance management practices.
Feedback on this reliability
article is appreciated. Send to info@idcon.com
For plant
maintenance consulting information. Please call (919) 847 8764.
More information available in our reliability
and maintenance books |
(part 1) (part
2)
Tough choices
The figures in this column describe an actual case where a pulp mill decided
to do whatever it took to cut costs—mainly through maintenance cutbacks.
The mill belongs to a big corporation and was a high-cost producer. When
the cost saving initiative started, pulp prices were low and profitability
was low, from a short-term perspective, compared with other mills in the
corporation. The fast-pace cost reduction actions included the following:
• Operations took over maintenance and only did maintenance work
that was judged necessary.
• Planning of work was not done.
• Scheduling ceased to exist.
• The Preventive Maintenance program was handed over to the operators,
without training them in what to do or how to inspect. The Preventive
Maintenance inspectors were laid off.
• Shutdown crews were merged with another mill that was a one-hour
drive from the mill.
• Painting programs were abandoned.
• Training of craftspeople stopped, etc.

Figure 1. The first two years maintenance costs
dropped, then started to increase. Reliability and quality production
throughput also went down and continued to do so for the six years before
reinstatement of basic maintenance processes.

Figure 2. Same data as in chart one but in financial
terms ($ values are per year). Short- term maintenance savings during
two years caused disastrous results after only three years.
NO LONG-TERM ADVANTAGE. In the first years
after the cost saving initiative began, maintenance costs dropped from
$35 million/year to $27 million/year, and results were hailed as good.
However, reliability soon started to decline. When the initiative started,
reliability was 93%, but bottomed out at 78% six years later, at a time
when pulp prices had doubled.
The drop of 15% in reliability, and even more in quality production output,
corresponded to a loss of more than 300,000 tons during some very good
years when product could have been sold at top prices. Financial losses,
due to low reliability resulting from the cuts in maintenance spending,
were conservatively estimated to have exceeded $1.2 billion during a three-year
period.
TIME TO TURN AROUND. After realizing the catastrophic
consequences of its cost saving initiative, the mill focused on bringing
its maintenance up to world-class status. Results have been very encouraging,
and today the mill is a top performer, with reliability now approaching
94%. Maintenance costs have gone up, but so has quality production throughput.
Manufacturing costs per ton are also lower.
The actions taken to bring maintenance to world-class status included:
• Reinstating Preventive Maintenance inspectors and revising the
Preventive Maintenance program;
• Bringing maintenance back as a central mill function;
• Developing a partnership between maintenance and operations;
• Focusing on planning and scheduling;
• Developing employee capabilities toward joint performance goals;
• Investing capital in new equipment and restoring worn out equipment
.
During the 16th annual Pulp & Paper Reliability
and Maintenance Conference in Atlanta, held jointly with Paper Summit
this past March, a similar experience was presented as a case study. For
copies of this presentation, please contact me at: info@idcon.com
|