You’re Doing it Wrong! Shutdown Schedule Compliance

Is your shutdown schedule compliance at 100%

When it comes to shutdown schedule being on time is paramount to getting your production going. But there are many reasons why teams are not sticking to the schedule.

Why shutdown schedules aren’t compliant

This picture is one you don’t want to see during a shutdown. 1 person working and 10 others standing around “supervising”. This is one of the most important aspects of a shutdown – proper scheduling and planning how we use our resources.

Another reason is emergency work, you stop doing the work that was planned and scheduled. But if the work scope isn’t correct you end up with scope creep, because you didn’t understand the work that was supposed to be done.

Again, if you are reviewing and scoping out the work during the work list phase you are likely going to under or over estimate the amount of time needed to complete work. Or it’s possible that the right trade is not available to complete a part of the work or maybe they are waiting around. For instance, the mechanical team is on hold because they are waiting for an electrician.

Another reason that the schedule may be delayed is not having the materials available and close to the job site. If they aren’t, a delay in the schedule is sure to occur.

Not getting the right permits can also be a schedule delay.

Uncontrollable problems that could affect your shutdown schedule compliance

You need to have contingency plans in place should an uncontrollable event happen during the shutdown. One time, we were working on a tank outside and suddenly a thunderstorm came up there was no way we could be working outside in those conditions, but because we had a contingency plan in place for an event like this, we were able to move to another indoor job and keep on schedule.

Need more advice about Shutdown Scheduling? Get our Practical Guide to Shutdown Turnaround Optimization book or come to our next training class.

At IDCON, we understand the pressure you face trying to build a reliable plant.
We provide side-by-side reliability and maintenance consulting and training designed to keep your equipment running.

For over 45 years, we’ve partnered with 100s of manufacturing plants around the world to eliminate the costs and the pressure caused by unreliable equipment. And we’d love to do the same for you.

Contact us today to see how we can help you keep your plant running.

Related Articles

Root Cause Failure Analysis

Root Cause Failure Analysis – IDCON’s Root Cause Problem Elimination Process We have named our process for problem solving training and elimination “Root Cause Problem Elimination™” instead of the commonly used

Read More »
Picture of Owe Forsberg

Owe Forsberg

CMRP, CAMA, VP of IDCON, INC.

Want weekly Reliability & Maintenance Tips?

Weekly Tip Signup Form

Best practices. Common sense. Pratical tips.
All designed to help you and your team keep your plant running

IDCON © 2020 All rights reserved

8-step-checklist-preventive-maintenance-program-download
Free Download & Video

8 Steps to Successfully Implement Preventive Maintenance

Reduce your costs with an effective PM program